Present Satge:
Work awarded to M/s. IVRCL Infrastructure Projects Limited, Hyderabad on 8.6.2010. Agreement was also concluded for a value of Rs.315.03 Crore on 2.7.2010.
The Progress of pipeline works are as follows:
| Description of work |
Total Quantity in km |
Pipe laid in km |
Pipe laid in % |
| Transmission main |
83.46 |
76.179 |
91 % |
| Feeder main |
52.058 |
46.161 |
89% |
| Internal Transmission main |
536.622 |
235.370 |
44% |
| Internal Network |
1636.430 |
29.800 |
2% |
The Progress of construction of civil works are follows:
| Description of work |
Total Quantity in nos |
No. of works Completed |
No. of works under progress |
| Union Master Balancing Reservoir |
5 |
2 |
3 |
| Panchayat Master Balancing Reservoir |
129 |
58 |
46 |
| Union Sump |
4 |
4 |
- |
| Panchayat Sump |
122 |
22 |
8 |
| Over Head Tank |
119 |
29 |
59 |
| Total |
379 |
115 |
116 |
Percentage of completion of work:
So far 59% of work has been completed under this Package.
Package III:
This Package consists of branch trunk main from trunk main to Package-II, feeder main etc., to a length of 1,572.27 Km. covering 5 Town Panchayat viz., B. Mallapuram, Harur, Kadathur, Kambainallur and Pappireddypatti and 1,083 habitations in three unions viz., Morappur, Harur and Papireddypatti . The population to be benefited from this Package is 4.40 lakh.
Present Satge:
Work awarded to M/s. L&T Ltd, Chennai on 22.12.2010. Agreement was also concluded for a value of Rs.164.05 Crore on 03.01.2011
The Progress of pipeline works are as follows:
| Description of work |
Total Quantity in km |
Pipe laid in km |
Pipe laid in % |
| Transmission main |
39.57 |
9.972 |
25 % |
| Feeder main |
22.025 |
2.347 |
10% |
| Internal Transmission main |
435.350 |
83.818 |
19% |
| Internal Network |
1002.415 |
- |
- |
The Progress of construction of civil works are follows:
| Description of work |
Total Quantity in nos |
No. of works Completed |
No. of works under progress |
| Union Master Balancing Reservoir |
4 |
- |
1 |
| Panchayat Master Balancing Reservoir |
96 |
3 |
34 |
| Union Sump |
13 |
- |
1 |
| Panchayat Sump |
62 |
2 |
3 |
| Break Pressure Tank |
2 |
- |
- |
| Over Head Tank |
124 |
22 |
9 |
| Total |
301 |
27 |
48 |
Percentage of completion of work:
So far 29% of work has been completed under this Package.
Package IV:
This Package consists of pumping main from common booster station at Moongilpatti to a length of 3,107.21 km. covering Hosur Municipality 3 Town Panchayat viz., Mathagiri (Now merged with Hosur Municipality), Kelamangalam, Thenkanikottai and 1,720 habitations in 5 unions viz. Veppanapalli, Kelamangalam, Thalli, Sulagiri and Hosur. The population to be benefited from this Package is 8.00 lakh.
Present Satge:
Work awarded to M/s. NCC-SMC- Pratibha-ECL(JV) Hyderabad on 16.9.2010. Agreement was also concluded for a value of Rs.387.54 Crore. on 9.10.2010.
The Progress of pipeline works are as follows:
| Description of work |
Total Quantity in km |
Pipe laid in km |
Pipe laid in % |
| Transmission main |
67.17 |
57.58 |
86% |
| Feeder main |
7.27 |
6.040 |
83% |
| Internal Transmission main |
854.81 |
298.562 |
35% |
| Internal Network |
2139.46 |
8.56 |
0.4% |
The Progress of construction of civil works are follows:
| Description of work |
Total Quantity in nos |
No. of works Completed |
No. of works under progress |
| Union Master Balancing Reservoir |
3 |
- |
3 |
| Panchayat Master Balancing Reservoir |
183 |
16 |
78 |
| Union Sump |
5 |
5 |
- |
| Panchayat Sump |
151 |
11 |
40 |
| Break Pressure Tank |
19 |
- |
3 |
| Over Head Tank |
49 |
- |
4 |
| Total |
410 |
32 |
128 |
Percentage of completion of work:
So far 48% of work has been completed under this Package.
Package V:
This Package consists of trunk main from Master Balancing Reservoir at Madam to Moongalpatti Sump and then Moongalpatti sump to Krishnagiri feeder mains etc., to a length of 2,949.55 Km. covering Krishnagiri Municipality,7 Town Panchayat viz., Karimangalam, Marandahalli, Palacode, Paparapatti, Bargur, Kaveripattinam, Nagojanahalli and 2,299 habitations in 5 unions viz. Palacode, Karimangalam, Bargur, Krishnagiri and Kaveripattinam . The population to be benefited from this Package is 9.00 lakh.
Present Satge:
Works awarded to M/s. L&T Ltd, Chennai on 22.12.2010 Agreement was also concluded for a value of Rs. 366.80 Crore on 03.01.2011.
The Progress of pipeline works are as follows:
| Description of work |
Total Quantity in km |
Pipe laid in km |
Pipe laid in % |
| Transmission main |
90.83 |
5.73 |
6% |
| Feeder main |
27.36 |
1.20 |
4% |
| Internal Transmission main |
687.138 |
238.198 |
35% |
| Internal Network |
1953.020 |
- |
- |
The Progress of construction of civil works are follows:
| Description of work |
Total Quantity in nos |
No. of works Completed |
No. of works under progress |
| Union Master Balancing Reservoir |
5 |
- |
3 |
| Panchayat Master Balancing Reservoir |
160 |
8 |
37 |
| Union Sump |
6 |
- |
1 |
| Panchayat Sump |
163 |
4 |
9 |
| Break Pressure Tank |
2 |
- |
1 |
| Over Head Tank |
238 |
1 |
16 |
| Total |
574 |
13 |
67 |
Percentage of completion of work:
So far 28% of work has been completed under this Package.
Fluorosis Mitigation Component:
M/s Symbiosis of Technology, Environment and Management (STEM), Bangalore, has been engaged as the Technical Support Organization (TSO) for implementation of this component and agreement has been concluded on 17.05.2010 by the PCE, Dharmapuri. The inception report of TSO containing the work plan and activities was approved by the Evaluation Committee on 13.12.2010. Training has been given to lab Technicians from Government Hospitals at Fluorosis Research and Rural Development Foundation, New Delhi. Training to all Government Doctors in Dharmapuri and Krishngiri completed. Teachers Training Materials printed. Training to 3200 teachers is proposed from December 2011.
The team of Doctors and Fluorosis Mitigation experts from Japan visited Dharmapuri and Krishnagiri Districts from November 21 – 26, 2011 to study the implementation and to share experience on interventions in Medical field.
Overall Completion:
So far 42 % of work has been completed.
The total expenditure so far incurred is Rs. 660.96 Crore.
It is targeted to commence the trial run of water supply works by December 2012.
| Package I |
|
 |
 |
Intake Works
|
Raw Water Pumping Main
|
 |
 |
WTP – Sand Filter
|
WTP –Filter Operation Building
|
 |
 |
| Booster Pumping Station
|
BPS – H.V. Sub Station & Pump House
|
| Package II |
|
 |
 |
| Laying of Pipeline at Puliyur Lake Area
|
Nagampatti – 3.00 LL Master Balancing Reservoir
|
| Package III |
|
 |
 |
| Harur TP – 1.00 LL Master Balancing Reservoir
|
Salamarathupatti– 1.00 LL Sump
|
| Package IV |
|
 |
 |
Ullukurukai – 30 LL Sump
|
Thinnur– 20LL Master Balancing Reservoir
|
| Package V |
|
 |
 |
Manufacturing of MS Pipe
|
Varatanapalli–1.50LL Master Balancing Reservoir
|
|